An explosion during a maintenance outage on February 17, 1999, destroyed the original Hawthorn Unit 5 boiler. In August 1999, B&W was released to design, supply, erect and commission a complete replacement boiler on an accelerated schedule. The new boiler began generating electricity in June 2001, only 22 months from project commencement.