Success Stories
From The Leader in Clean Power Production Technologies
Hawthorn Unit 5 Plant Rebuild — Missouri, USA
Success Story
Kansas City Power & Light
Kansas City, Missouri
An explosion during a maintenance outage on February 17, 1999, destroyed the original Hawthorn Unit 5 boiler. In August 1999, B&W was released to design, supply, erect and commission a complete replacement boiler on an accelerated schedule. The new boiler began generating electricity in June 2001, only 22 months from project commencement.
Plant Owner
Kansas City Power & Light
Plant Name
Hawthorn Unit 5
Location
Kansas City, Missouri
Owner’s Consulting Engineer
Burns & McDonnell
B&W Scope
- Complete boiler island from coal-conveying system to stack, including:
- structural steel
- dry FGD
- fabric filter
- ash systems
- electrical, including motor control centers, switchgear, and wiring
- auxiliary piping systems
- critical piping to the turbines
- Construction by Babcock & Wilcox Construction Co., Inc. (BWCC), a B&W subsidiary
- Architectural services for the boiler island
- Startup and commissioning services
Boiler Specifications
- Type: Pulverized coal-fired radiant drum boiler (RB Carolina-Type)
- Design fuel: Low sulfur Powder River Basin coal
- Capacity: 550 MW net
- Steam flow: 4,000,000 lb/h (504 kg/s)
- Superheater outlet pressure: 2600 psig (17.9 MPa)
- SH/RH outlet temperature: 1005/1005 F (541/541 C)
Environmental Equipment
- DRB-4Z® low NOx burners and overfire air
- Selective catalytic reduction (SCR) NOx removal system
- Dry flue gas desulfurization (FGD) system
- Pulse jet fabric filter (PJFF)
Other Equipment Supplied by B&W
- B&W Roll Wheel® pulverizers, Series 89
- Boiler cleaning system (sootblowers and waterwall blowers) by B&W
Contract Order: 1999
Commercial Operation: 2001
Project Facts
- Rebuilt unit’s capacity uprated from 476 MW to 550 MW
- PJFF was built on the foundation of one of the original electrostatic precipitators (ESP) and adapted the existing hoppers and support steel.
- Even with a compressed schedule and the constraints of rebuilding within an existing site, the project achieved every major milestone. Sectional Side and Plan Views of Hawthorn Unit 5